Stage-sensitive inspection
Quality Insulation Installation must be inspected before concealment.
QII verifies construction details that can no longer be fully observed after drywall or other finish materials are installed. Coordination with the rater must begin before insulation work is covered.
Typical inspection sequence
Plan before insulation and drywall.
Review the CF1R
Confirm that QII is required and identify the applicable assemblies.
Framing and air-sealing stage
Required cavities, penetrations, backing and air-barrier details must remain visible.
Insulation stage
Insulation must be installed to the required quality with gaps, compression and voids addressed.
Documentation
Applicable verification is completed after the required stages pass and project records are ready.
Do not cover first
Visibility matters.
- Wall, ceiling and floor cavities within the QII scope
- Air-sealing at penetrations and framing transitions
- Insulation fit around wiring, plumbing and mechanical work
- Attic, roof and raised-floor assemblies when applicable
- Areas identified for correction during an earlier stage
If work is already concealed, contact the project energy consultant and rater before removing materials or assuming an alternative. Available options depend on the project, approved documents and enforcement agency.
Schedule the right stage
Send the plans and CF1R early.