CF1R — Certificate of Compliance
Describes the approved energy design, project features and applicable field-verification measures. It is generally prepared during design or permit review by the responsible documentation author.
Document responsibilities
The documents work together, but they are not completed by the same person or at the same project stage.
Describes the approved energy design, project features and applicable field-verification measures. It is generally prepared during design or permit review by the responsible documentation author.
Records applicable installed features and is completed by the responsible installer or contractor for that scope. A rater does not replace the installer’s responsibility.
Records applicable independent field verification performed by the ECC rater after the required inspection or diagnostic test.
Before testing
The rater completes applicable verification within the rater’s scope. Installers complete their installation documents. The documentation author manages the approved compliance design. The building department controls inspections, final approval and permit closure.
Missing a document?
We can help identify the missing step and the responsible project participant.